Library and Academic Computing News         Fall 2001

Update on New Library Building
The Contractor for the new library building, Hitt Inc, has begun preliminary work - obtaining city permits and surveying nearby properties before they begin driving piles.  The plans call for a two-year construction period.  Here's the preliminary schedule for Year 1: 
  • 4 weeks  - site preparation began August 1
  • 10 weeks - driving piles - tentatively beginning September 1. The architects estimate that each pile will be approximately 90-110 feet deep to ensure a firm foundation. 
  • 38 weeks - structural work to frame the building.
RSS Library
Academic Computing
Request a Book for the Library
Book Budget
Contact your Department Liaison.
The Lurker, an electronic publication of the Robert Scott Small Library and Academic Computing, is designed to update faculty on new information services and resources.  Please send your comments, articles, and suggestions to: 
Jared Seay:  seayj@cofc.edu (3-1428) 
Sheila Seaman:  seamans@cofc.edu (3-5530).