  • Construction documents for the conversion of Craig Cafeteria to an admissions hub continued to be developed in November. The project is scheduled to be bid out in January.
  • Interior demolition of the old John Kresse Arena occurred in November. Steel work for the racquetball courts will begin in January.
  • Electricity will be provided to the Cato Center in December, with window installation beginning in late December/early January.
  • Moisture-resistant drywall was installed in some areas of the new science center, and concrete grade beams and electrical tie-ins were also completed. All other utilities tie-ins should be complete in early December, and slab work and direct-burial piping is scheduled for completion in December. Roofing has begun and may be complete by the end of January, which is also when flood walls are expected to be installed.